How to Complete a Certificate Renewal task
How to complete a Certificate Renewal task
-
The Complete Certificate Renewal Task
window displays. Review the Person and Certificate information 1. Review the Actioned On and By 2, and change if required. Choose and Outcome
3 of ‘Renewed’ or ‘Not Renewed’. If ‘Renewed’ is selected, enter a ‘From’ and ‘To’ 4 date of the renewed Certificate period. Click the ‘Add Comment’ 6 icon to add a Comment, which will display in the comment list 7 when saved. (Or, click the Cancel 8 icon to cancel.)
-
The Certificate Renewal Task is completed, and is no-longer displayed in the Current Tasks list. The New Certificate record is created and displayed in the SMCR Certificates
list. Click on the Certificate to open the record.
-
The new Certificate record is displayed containing the next Certified dates 1, and the ‘Create Renewal Task’ 2 switch selected to generate for the next Certified period.
Related Articles
Certificate Renewal Tasks - Open Task via Email notification link
Open Task via Email notification link Open the notification email containing the Certificate Renewal Task completion request. Click the here 1 link in the 'To complete this Task… ' line, to open the Completion task window.
Certificate Renewal Tasks - Certificate record Renewal sent
Certificate record Renewal sent Access Certificate Renewal Tasks. Click on the Certificate record. The Create Renewal Task option is replaced with the a message 1 that Task has been sent, when it was sent and who is the Actioned By.
Certificate Renewal Tasks - Create a Certificate Renewal Task
This function allows the creation of a scheduled task to re-certify a person. Access Certificate Renewal Tasks. Click on the Certificate record 1 you wish to create a Renewal task for. The Certificate for the select Person window displays. Click the ...
How to access Certificate Renewal Tasks
Open Task via My Summary Current Tasks tab From the Main Menu, select SMCR | My Summary. Click the Current Tasks tab. Find your SMCR Certificate Renewal Task (using a filter or search). Click the ‘Complete the Task’ 1 icon.
Adding (Scheduling) the KRI Task
Adding (Scheduling) the KRI Task The KRI’s purpose is to record each measure as required. So, unlike a Compliance Process which can have multiple Process Control tasks, the KRI only has one task, record the measurement. Hence, the Task tab only ...